Figure 4-53 Installing slanting beams
Step 6 Connect the beam to the wall by routing M10x30 stainless steel bolts through the
reserved tapped holes on the left and right sides at the top of the base.
----End
4.6 (Optional) Installing a Low Temperature
Component
4.6.1 Checking the Nitrogen Pressure
Context
Before delivery, low temperature components are injected with nitrogen to 0.2–0.6
MPa. Before connecting pipes, the nitrogen inside pipes must be discharged.
Nitrogen must be discharged; otherwise, air jets emitted during pipe welding may
cause bodily injuries.