Huawei SUN2000 MB0 Series User Manual page 46

Hide thumbs Also See for SUN2000 MB0 Series:
Table of Contents

Advertisement

SUN2000-(12K-25K)-MB0 Series
User Manual
requirements of the PE cable. For some power grid types, if the output side of the
inverter is connected to an isolation transformer, ensure that the inverter is
properly grounded and set Grounding abnormal shutdown to Disable so that
the inverter can run properly.
Procedure
Step 1 Crimp an OT terminal.
● Avoid scratching the core wire when stripping a cable.
● The cavity formed after the conductor crimp strip of the OT terminal is crimped
● Wrap the wire crimping area with heat shrink tubing or insulation tape. The
● Use a heat gun carefully to avoid heat damage to the equipment.
Issue 01 (2023-04-30)
According to IEC 62109, to ensure the safe operation of the inverter in the
case of PE cable damage or disconnection, properly connect the PE cable of
the inverter and ensure that it meets at least one of the following
requirements before the grounding detection function becomes invalid.
If the PE terminal of the AC connector is not connected, the PE cable on
the enclosure must be a single-core outdoor copper cable with a cross-
sectional area of at least 10 mm
Use cables with the same diameter as the AC output power cable and
ground the PE terminal on the AC connector and the ground screws on
the enclosure.
In some countries and regions, the inverter must have additional ground
cables. In this case, use cables with the same diameter as the AC output
power cable to ground the PE terminal of the AC connector and the ground
screws of the enclosure, respectively.
NO TICE
must wrap the core wire completely. The core wire must make close contact
with the OT terminal.
heat shrink tubing is used as an example.
Copyright © Huawei Digital Power Technologies Co., Ltd.
5 Electrical Connections
2
.
40