Shelter, wiring guide for 12ft solar powered unit
Installation Guide
Order of operations:
1.
Anchor kit installation
2.
Frame assembly
3.
Roof assembly
4.
Wall glass assembly
5.
Wiring connections
Tools Required
• wiring tools
• 3/32" hex key
• 3/16" hex key
• 5/16" Socket wrench
• Flat head screwdriver or ¼" socket wrench
Included components:
• Uplights, with wiring harnesses, pre‐installed in front horizontal beam
• Down lights, with wiring harness and connectors, one per rafter
• Wayfinding lights, with wiring harness, two per unit
• Glass solar panel with brackets and attaching hardware
• 16 batteries with wiring harness
INSTALLATION: 
Order of installation: Install batteries in front horizontal beam. Batteries are installed in a Velcro harness 
to facilitate easier removal, if needed. Install downlights. Install wayfinding lights. Connect wiring 
harnesses to driver. Install fuse. Run test of lights.
1.
Remove access cover in horizontal beam near front right post. Ensure Velcro strip is installed on 
front horizontal beam. Secure one end of long Velcro harness to the top half of the strip mounted in 
the horizontal beam. Connect (‐) lead of the battery harness to the first battery (‐). Install short 
jumper harness to the positive pole of the battery as shown in Fig. 2. Attach the other end of the 
jumper harness to the second battery. Install the second battery. Repeat this process for batteries 3 
th
and 4, with the 4
battery hooking up to the main wire harness (+) connector. Repeat this process 
for the remaining batteries. See Fig. 4 for wiring reference. Slide each battery into Velcro harness as 
it is being installed. Once all batteries are installed, twist Velcro strap and secure it to the bottom of 
the mating Velcro strip in the horizontal beam, see Fig. 3.
2.
First rafter downlight: make connection at front horizontal to quick disconnect. Push rafter light 
connection through grommet. Grommets may be removed to push wires through and then 
reinstalled, if necessary. See Fig. 5. Using a 3/32" hex key, attach downlight to rafter using (6) #8‐32 
x 5/16 socket button head cap screws, located in hardware pack #62599. Do not overtighten screws.
3.
Install remaining rafter downlights: make connection to quick disconnects. Push connection through 
grommet on front horizontal beam. Attach downlight to rafter, see Fig. 5.
4.
Unused grommets on rear horizontal beam can be sealed with clear or black silicone (supplied by 
others).
5.
Install left and right side rafter skins, with the sharper angle of the skin toward the front of the 
rafter. See Fig. 6. Rafter skins have a boss on the bottom flange that hooks into the downlight, see 
Fig. 6. Hook the bottom of the skin into position and then rotate the top of skin up to the rafter 
beam. Using a 3/16" hex key, install (2) ¼‐20 x ¾" socket head cap screws, located in hardware pack 
#62599. Tighten until gap between light and rafter skin is gone and rafter skin does not rattle. Do 
not overtighten screws. 
6.
Wayfinding lights: Run wiring harness up through front vertical post. On the front left side of the 
unit, remove the access cover on the front horizontal beam. Make connection from the wiring 
harness to the quick disconnect located in the beam. Secure LED to front vertical post, using (4) 8‐32 
x ½" hex head machine screws with external tooth lock washer, located in hardware pack #62810, 
see Fig. 7. Before final tightening of screws, ensure only the lens from the light is showing through 
the front opening. Repeat for opposite side. Install cover plates, using (2) ¼‐20 x ½" socket head cap 
screws, located in hardware pack #62607, see Fig. 8. Make connection to pre‐installed wiring 
harness labeled "wayfinding light".
7.
Driver plate assembly: Attach driver plate to front horizontal beam, in the front right access 
location, see Fig. 9.
8.
Make connections to PDM as labeled: Uplight, Wayfinding (x2), Downlight, see Figs 10 and 11. Make 
connections to Morningstar unit, in the order noted on the device. When all of the wiring 
connections are complete, install the fuse, see Fig. 9.
9.
Follow the instructions for the Morningstar unit to test the lights. Replace access cover.
Date: February 21, 2019
www.landscapeforms.com
Ph: 800.521.2546
Page 1 of 5

Advertisement

loading

Summary of Contents for Landscape Forms Connect 2.0

  • Page 1 Connect 2.0 Shelter, wiring guide for 12ft solar powered unit Date: February 21, 2019 Installation Guide www.landscapeforms.com Ph: 800.521.2546 Order of operations: INSTALLATION:  Anchor kit installation Order of installation: Install batteries in front horizontal beam. Batteries are installed in a Velcro harness  Frame assembly to facilitate easier removal, if needed. Install downlights. Install wayfinding lights. Connect wiring  Roof assembly harnesses to driver. Install fuse. Run test of lights. Wall glass assembly Remove access cover in horizontal beam near front right post. Ensure Velcro strip is installed on  Wiring connections front horizontal beam. Secure one end of long Velcro harness to the top half of the strip mounted in  the horizontal beam. Connect (‐) lead of the battery harness to the first battery (‐). Install short  Tools Required jumper harness to the positive pole of the battery as shown in Fig. 2. Attach the other end of the  jumper harness to the second battery. Install the second battery. Repeat this process for batteries 3  • wiring tools and 4, with the 4 battery hooking up to the main wire harness (+) connector. Repeat this process  • 3/32” hex key for the remaining batteries. See Fig. 4 for wiring reference. Slide each battery into Velcro harness as ...
  • Page 2 Connect 2.0 Shelter, wiring guide for 12ft solar powered unit Date: February 21, 2019 Installation Guide www.landscapeforms.com Ph: 800.521.2546 ASSEMBLE WITH CARE! Pangard II Polyester Powdercoat is a strong, long‐lasting finish.  To  WIRING HARNESS LEAD – protect this finish during assembly, place unwrapped powdercoated parts on packaging foam or  END WITHOUT FUSE other non‐marring surface.  Do not place or slide powdercoated parts on concrete or other hard or  textured surface – this will damage the finish causing rust to occur.  Use touch‐up paint on any  BATTERY gouges in the finish caused by assembly tools. DRIVER PLATE UPLIGHTS, PRE‐INSTALLED FACTORY‐INSTALLED VELCRO STRIP VELCRO HARNESS...
  • Page 3 Connect 2.0 Shelter, wiring guide for 12ft solar powered unit Date: February 21, 2019 Installation Guide www.landscapeforms.com Ph: 800.521.2546 FUSE Fig. 4 – battery connection diagram for 12ft shelter RAFTER 1/4‐20 x 3/4” SHCS  (2) PER SIDE FRONT  RAFTER  HORIZONTAL  SKIN BEAM GROMMET ATTACHMENT  POINT (3 PER SIDE) HOOKS INTO   QUICK DOWNLIGHT DOWNLIGHT DISCONNECT Fig. 6 – install rafter skins Fig. 5 –...
  • Page 4 Connect 2.0 Shelter, wiring guide for 12ft solar powered unit Date: February 21, 2019 Installation Guide www.landscapeforms.com Ph: 800.521.2546 (2) ¼‐20 x ½  SOCKET  HEAD CAP SCREW WIRING HARNESS  FOR WAYFINDING  LIGHT COVER PLATE Fig. 8 – Install wayfinding  WAYFINDING  light cover plate LIGHT  ASSEMBLY (4) 8‐32 x ½ HEX HD  MACHINE SCREWS WITH  LOCKTOOTH WASHERS Fig. 7 – Install wayfinding lights Page 4 of 5...
  • Page 5 Connect 2.0 Shelter, wiring guide for 12ft solar powered unit Date: February 21, 2019 Installation Guide www.landscapeforms.com Ph: 800.521.2546 FUSE LOCATION MORNINGSTAR  UNIT Fig. 10 – solar wiring connections (2) ¼‐20 x ½ SOCKET HEAD CAP SCREWS Fig. 9 – Install driver plate assembly, front right access hole Fig. 11 – solar wiring diagram Page 5 of 5...