Summary of Contents for Huawei FusionModule1000A20
Page 1
FusionModule1000A20 Prefabricated All-in-One Data Center V200R003C10 Installation Guide Issue Date 2020-01-15 HUAWEI TECHNOLOGIES CO., LTD.
Page 2
Notice The purchased products, services and features are stipulated by the contract made between Huawei and the customer. All or part of the products, services and features described in this document may not be within the purchase scope or the usage scope. Unless otherwise specified in the contract, all statements, information, and recommendations in this document are provided "AS IS"...
3.3 Checking the Installation Environment Check the site requirements one by one, and start installation only after all requirements are met. Huawei will not be liable for any consequences caused if the installation environment does not meet the requirements. Mark the security zone: Use red caution belts to delimit a security zone, clean up obstacles in that zone, and place construction signs and warning signs in eye-catching positions.
Prerequisites The pre-fab. modules have been installed. The rectifier delivered onsite is complete and intact after unpacking and acceptance. If any problem is found, contact your local Huawei office. Preparations Tool: none Material: rectifier Skill requirement: skilled technician ...
Prerequisites The pre-fab. modules have been installed. The rectifier delivered onsite is complete and intact after unpacking and acceptance. If any problem is found, contact your local Huawei office. Preparations Tool: none Material: rectifier Skill requirement: skilled technician ...
Page 73
Step 2 Remove the protective foam from the battery and check whether the battery is intact or leaks. If the battery is damaged or leaks, contact Huawei technical support to replace the battery. Step 3 Connect the reserved battery cable.