6

Commissioning

6.1
Preliminary checks prior to start-up
The following points must be checked before commissioning:
The supply power must be switched off.
The supply power must match information on the name plate.
The pin assignment must correspond to the connection diagram.
The unit must be grounded.
The temperature limits must be observed.
6.2
Commissioning the unit
Important
Please ensure compliance with the specific instructions for installing explosion-proof
equipment. These can be found in section 11 "Ex relevant specifications".
6.2.1
Switching on the supply power
After switching on the supply power, the display (if in use) shows the current flow after a few
seconds.
6.2.2
Device configuration
The device can be factory calibrated to customer specifications upon request. If no customer
information is available, the device is delivered with factory settings (see Standard display
format on page 62).
6.3
Information on voltage/current consumption
The switch-on response meets the requirements set out in draft DIN IEC 65C/155/CDV, June
1996. The mean current consumption of the device is 10 mA. In the event of an error, the FDE
(fault disconnection electronic) function integrated into the device ensures that the current
consumption can rise to a maximum of 13 mA. The upper limit of the voltage is electronically
limited. The supply voltage for the standard design (model V_40 / S_40)) is 9 ... 32 V DC. The
intrinsically safe design (model V_4A / S_4A) has a supply voltage range of 9 ... 24 V DC.